Lake Delia promenade: the site board gave completion as 24 September, the tender required 5 months from the notice to proceed
The 24 September 2026 deadline on the construction site board of the Lake Delia promenade has passed, and the works are continuing. The tender documents, however, require 5 months of execution from the notice to proceed (start order), and the contract is valid until 31 December 2026. Counted from the start date on the board, 24 June, the 5 months would end on 24 November. According to the model agreement approved in Ungheni, the money from Cluj-Napoca is paid after the works are accepted.